We are renovating our kitchen. We picked IKEA's Akurum/Stat kitchen, and will keep pretty much the same layout we currently have, with some minor tweaks. And we're going to do the whole thing ourselves. Well, at least that's the plan.
The cabinets are supposed to arrive on Monday. I believe it when I see it. Today I finished making space in the garage. You can park a car in there again. yay. On Monday, this space will be filled with boxes, and boxes, and boxes. Then over the course of the week, I will demolish the row of cabinets on the backwall of the kitchen. This is where the fridge, the oven and the microwave are located. So until I'm done there won't be fresh bread or cake in the house. But we can continue to use the cooktop, so we'll have some warm food.
I'm planning 2 days for setting up the 5 large cabinets, so I should be done with this before I fly out to Seattle the week after.
Depending on how this works out, we'll tackle the other side of the kitchen, with sink and countertop. This will involve some nasty work to get rid of backsplash tiles, fixing drywall afterwards, and also replacing the current florescent lighting with recessed lighting. For the electrical and the dry wall work we'll get contractors, they'll do a better job than I could, and for anything dealing with house electrical it's a good idea to get someone who knows what they are doing.
Once this is all done, I'll redo the floor.
The first phase should take about a week of elapsed time. The second phase, due to contractors and more complicated arrangement, I'm estimating about 2 weeks. And the floor will be a good weekend's work. So overall, I'm targeting to be done with this in early March (taking work assignments where I need to be out of town into account). Let's see how that all works out.